By providing your contact information to Julio Nunez, your personal information will be processed in accordance with Julio Nunez's Privacy Policy. By checking the box(es) below, you consent to receive communications regarding your real estate inquiries and related marketing and promotional updates in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. You may opt out of receiving further communications from Julio Nunez at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe.
Thank you for your message. I'll be in touch with you shortly.
Explore My Properties
Two off-white beach chairs facing turquoise Atlantic water on a quiet sandy beach, with sea grapes and sea oats at the edge.

Midtown Beach Has a Short Season Left Before the Seawall Work. Here's How the Island's Beach Day Rearranges.

November 12, 2026

On Wednesday, November 4, the stairs at Brazilian Avenue opened again and Midtown Beach had a way in after more than a week shut. Two blocks south, the Chilean Avenue stairs stayed closed. Chief lifeguard Craig Pollock told the Palm Beach Daily News that the sand around them had washed out. In its November 6 update, the Town said the Chilean entrance would stay closed until further notice.

The erosion closure was a short preview. Construction on the new Midtown seawall is scheduled to start in January 2027 and run through summer 2028. When it does, normal beach access between Royal Palm Way and Gulfstream Road closes for the whole job. That makes the weeks between now and January the last stretch of Midtown as the island's go-to beach until 2028. For about 18 months, the island's beach day will center on Phipps Ocean Park and the north end.

The Week the Ocean Closed It First

For about a week, high water closed Midtown before any construction crew did. The Palm Beach Daily News reported on November 2 that the beach had been closed for a week because of erosion and dangerous ocean conditions. Pollock said access still wasn't safe while water pushed up against the dunes at high tide.

That week showed what the island looks like without its central beach. The Palm Beach Civic Association describes Midtown as one of only two public beaches in town with lifeguards. Losing it for a week moves the beach day somewhere else. Losing it for a year and a half changes the island's routine.

Why the Town Chose One Long Closure Over a Longer Partial One

The 2,715-foot wall runs from Royal Palm Way south to Gulfstream Road. It is nearly 100 years old. Town officials have said it isn't about to fail, but engineering reports put it near the end of its useful life. Murray Logan Construction of West Palm Beach is the design-builder. The project is expected to cost $20 million or more, including the $1.5 million the Town Council set aside in July for design and planning.

At its October meeting, the council was briefed on two ways to build it and backed the faster one.

Approach Estimated duration Beach access during work Cost relative to full closure
Single continuous build, endorsed by council About 18 months Normal access closed Baseline
Phased build About 32 months Partial access kept Estimated 50 to 100 percent higher

WFLX put it more simply: the Town says doing the work in sections would have taken twice as long and cost twice as much. The timing also depends on sand. Jake Hurley, the Town's senior project engineer and manager for the seawall, told WFLX that the Town "just completed our renourishment cycle," so sand is available to protect the wall while it is built. He added that the Town has been working on funding and permits since 2020.

Sea turtles set the calendar too. Hurley told WFLX that nesting season is "a major contributing factor in how we schedule the construction" and that crews "cannot be on the beach unless we have a berm already constructed there."

What You Can Still Do on That Stretch of Sand

The closure covers the access points, but the shoreline itself stays reachable at times. Hurley described it to WFLX this way:

"We can't close the ocean, so there will be times when you'll be able to traverse the beach north-south as long as you are more towards the water side."

That walkable strip sits east of a berm between the ocean and the work zone. The berm keeps nesting turtles out of the construction site and keeps people out of it too, and there will be fencing on that side whatever construction method is used. In practice, a walk along the waterline from a beach to the north or south can pass Midtown. Setting up a chair and umbrella below the Worth Avenue Clock Tower cannot. Hurley said the Town closed the access points because "we don't believe there's a safe way for us to bring people from the roadway onto the beach."

South Ocean Boulevard stays open in both directions during construction. Hurley told the council he expects better traffic because people from off the island won't be driving over to park at the beach.

The Wall That Comes Back, and the Park Behind It

The new wall is designed to look like the one it replaces. Hurley told WFLX that the part of the current wall visible above ground is decorative, and the structural part is underground. The Town tracked down the original scallop molds, which he believes date to the 1980s, so the new wall will match the old one's shape and color. On average it will be about six inches higher and will sit a bit farther east. At the Worth Avenue Clock Tower, the Town is permitted to build seaward because the old wall sits directly against the landmark.

The project team is also recommending a new beach access at the north end of the project. Hurley acknowledged to WFLX that "there is a lot of people who are jumping the wall."

The Midtown Beach Linear Park, the strip of green that runs alongside the wall, gets a separate makeover budgeted at about $4 million. Construction is planned for near the end of the seawall work. The design presented to the council includes:

  • 15,000 more square feet of open space, a 48 percent increase over the current park
  • One wider sidewalk replacing the two existing ones, plus new benches and landscaping
  • A new stair access to the beach at Royal Palm Way
  • A terrace at the Worth Avenue Clock Tower so people can walk through the tower for a better ocean view
  • Traffic islands on South Ocean Boulevard and added pedestrian crossings at Brazilian Avenue and Royal Palm Way

Town Engineer Patricia Srayer said the goal is to keep as many of the park's 42 coconut palms as possible. Trees that have to move will be relocated and replanted in the park, and some will likely be replaced.

Where the Beach Day Goes in the Meantime

Council member Lew Crampton, who lives in the South End, raised the question at the council's September 8 meeting. He said people who can't use Midtown will likely head to the beaches east of Sunrise Avenue and to Phipps Ocean Park. "Those folks are going to go south, and you are going to have a potential overload there," he said, as reported by the Palm Beach Civic Association.

Phipps is coming back from its own long closure just as Midtown's begins. The Preservation Foundation of Palm Beach designed the redevelopment around native Florida plants and the coastal setting. The plan adds recreation areas, moves the Little Red Schoolhouse to higher ground near the dune, and puts it next to a new Coastal Restoration Center nursery for native plants. The Palm Beach Daily News reported that the landscape is meant to show off native plants that once grew along the South End. Raymond Jungles is the landscape architect and master-plan designer.

The Town and the Foundation are holding the ribbon-cutting and grand opening on the morning of Thursday, November 19, at 2201 South Ocean Boulevard. Admission is free.

Parking matters more once the island has one less beach. The Town says 2027 Parkmobile and Residential Parking Permits will be released in late November 2026, and its Park in Palm Beach page carries the details.

The Calendar From Here

  1. Now: Midtown is open at Brazilian Avenue. The Chilean Avenue entrance stays closed until further notice.
  2. November 19: Phipps Ocean Park ribbon-cutting and grand opening.
  3. Late November: 2027 Town parking permits go on sale.
  4. December: The Town hopes to bring Murray Logan's guaranteed maximum price, the all-in cost of the seawall, to the council.
  5. January 2027: Seawall construction is scheduled to begin and normal Midtown access closes.
  6. Summer 2028: Planned completion of the seawall. The Linear Park rebuild starts toward the end of that work.

The project team plans to hold more community meetings as the details are finalized.

If you live in one of the buildings along South Ocean Boulevard, or you're deciding whether to rent out a seasonal unit near Worth Avenue during the construction, the seawall schedule will shape your next two winters. South Florida Luxe Life tracks projects like this one block by block. We can talk through what the Midtown timeline means for your property and your plans. Schedule Your Free Consultation.